| A group of developers is building a new shopping center. A consultant for the developers has constructed the following project network and assigned activity times, in week
[Page 373] Determine the earliest and latest activity times, activity slack, critical path, and duration for the project. |
| A farm owner is going to erect a maintenance building with a connecting electrical generator and water tank. The activities, activity descriptions, and estimated durations are given in the following table:
Activity | Activity Description | Activity Predecessor | Activity Duration (weeks) |
a | Excavate |
| 2 |
b | Erect building | a | 6 |
c | Install generator | a | 4 |
d | Install tank | a | 2 |
e | Install maintenance equipment | b | 4 |
f | Connect generator and tank to building | b, c, d | 5 |
g | Paint finish | b | 3 |
h | Check out facility | e, f | 2 |
(Notice that the activities are defined not by node numbers but by activity descriptions. This alternative form of expressing activities and precedence relationships is often used in CPM/PERT.) Construct the network for this project, identify the critical path, and determine the project duration time.
jawab
10.
|
|
|
|
|
| 6,3 |
|
|
|
|
|
|
|
| 7 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| b,6 |
| e,4 |
| h,2 |
|
|
|
| 2 |
| 5 |
| 8 |
|
|
|
|
|
|
|
|
|
|
| a,2 |
| c,4 |
| f,5 |
|
|
start |
| 1 |
| 3 |
| 6 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| d,2 |
|
|
|
|
|
|
|
| 4 |
|
|
|
|
|
|
|
|
|